Report for October 2021
- Report Date
- October 2021
- Report Date
- October 2021
Achievements in last period
- The project is completing a procurement process
- The decision has been taken to move the admins to SSO as part of the migration
- Work is underway to understand and agree all technical decisions that have to be made on data provision and email set up
- The project manager has been reallocated to another project with a higher priority. The programme manager Susan Ridder-Patrick will now complete this project as the project manager
Issues
- The planning milestone deadline has had to be extended to 22nd November. This is the second time that this deadline has been extended. The ideal window for the stakeholders to make the move to the cloud is the end of November to the beginning of December. This change to the planning deadline puts this at risk and so the project has been moved to amber. This risk is detailed in risk 7. The full impact of this will be known once planning can be completed.
Next steps
- Finalise procurement activities
- Complete project plan and brief
Milestones
Stage | Milestone | Due Date |
---|---|---|
Plan | Completion of project brief | 22-Nov-2021 |
Deliver | Delivery | 17-Dec-2021 |
Close | Close | 21-Jan-2021 |
- Approved budget
- 50.0 days
- Activity this month
- 4.4 days
- Activity this year
- 10.4 days
- Activity to date
- 10.4 days
- Estimate to complete current year
- 39.6 days
- Estimate to complete future years
- 0.0 days