September RAG Status Report
- Report Date
- September 2024
Achievements this Period
- Sent out the Reminder email to students on 11th September
- Successfully closed the Review on 27th September with 10,892 returns, about 56% completion rate. This is more than the previous year's 7,784 submissions and is considered a great success for the project team.
Issues
- No issues
Next Steps
- Work on the recommendations for students and send out the personalised emails to those who submitted by 28th October.
- Review Task Breakdown Schedule with the Project Team to confirm tasks and timing/duration of work for future Review cycles.
Milestones
Stage | Milestone | Due Date | Previous Date | Complete |
---|---|---|---|---|
Deliver | Review Recommendations sent to Students | 28-Oct-2024 | No date available | No |
Close | Task Breakdown Review Sign-Off | 13-Nov-2024 | No date available | No |
Close | Closure (Major Milestone) | 29-Nov-2024 | No date available | No |
- Approved budget
- 45.0 days
- Activity this month
- 2.3 days
- Activity this year
- 19.3 days
- Activity to date
- 30.9 days
- Estimate to complete current year
- 13.8 days
- Estimate to complete future years
- 0.0 days