October RAG Status Report
- Report Date
- October 2024
Achievements this Period
- Recommendation emails to students was sent out on 28th October without any issues.
- Began work on completing D3.1
- Reviewed Task Breakdown Schedule with the Project Team to confirm tasks and timing/duration of work for future Review cycles. This includes a RACI for the tasks in the work package.
- A preliminary analysis on the effort from the RACI and Asta submissions was drafted and will be presented alongside the deliverable at project closure.
Issues
- No issues
Next Steps
- Agree and sign off on the Task Break Down for Deliverable 3.1
- Obtain Project Closure
Milestones
Stage | Milestone | Due Date | Previous Date | Complete |
---|---|---|---|---|
Close | Task Breakdown Review Sign-Off | 13-Nov-2024 | No date available | No |
Close | Closure (Major Milestone) | 29-Nov-2024 | No date available | No |
- Approved budget
- 45.0 days
- Activity this month
- 5.8 days
- Activity this year
- 25.3 days
- Activity to date
- 36.9 days
- Estimate to complete current year
- 5.7 days
- Estimate to complete future years
- 0.0 days