October RAG Status Report

Report Date
October 2024

Achievements this Period

  • Recommendation emails to students was sent out on 28th October without any issues.
  • Began work on completing D3.1
    • Reviewed Task Breakdown Schedule with the Project Team to confirm tasks and timing/duration of work for future Review cycles. This includes a RACI for the tasks in the work package.
    • A preliminary analysis on the effort from the RACI and Asta submissions was drafted and will be presented alongside the deliverable at project closure.

Issues

  • No issues

Next Steps

  • Agree and sign off on the Task Break Down for Deliverable 3.1
  • Obtain Project Closure

Milestones

Stage Milestone Due Date Previous Date Complete
Close Task Breakdown Review Sign-Off 13-Nov-2024 No date available No
Close Closure (Major Milestone) 29-Nov-2024 No date available No
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Time
No Change
Cost
No Change
Scope
No Change
Overall
No Change
Has formal escalation taken place?
No
Activity
Approved budget
45.0 days
Activity this month
5.8 days
Activity this year
25.3 days
Activity to date
36.9 days
Estimate to complete current year
5.7 days
Estimate to complete future years
0.0 days

Project Info

Project
Making Transitions Personal Review 24/25
Code
STU272
Programme
Student Services (STU)
Management Office
ISG PMO
Project Manager
Alexandra Mezeul
Project Sponsor
Alex Carter
Current Stage
Close
Status
Closed
Start Date
28-Jun-2024
Planning Date
24-Jul-2024
Delivery Date
21-Aug-2024
Close Date
27-Nov-2024
Overall Priority
Normal