Project Activity - w/c 20th May

  • Ongoing discussions with team members on TTI strategy; issue escalated to WIS. Confirmed that issue highlighted to Fraser Muir, with team to progress direct with schools
  • Strategy for approach and alternative options identified
  • Accessibility discussions ongoing - agreed that likely a full Equality Impact Assessment will be required.
  • 2 new issues raised by SACS investigated and closed - no escalation required
  • Issues with Eugex feed reviewed and scale of issues agreed; strategy for PP engagement agreed
  • Timetable for deployment highlighted to sponsor as at risk - alternative proposal put forward; with sponsor to review

Project Info

Project
PebblePad Upgrade 2013
Code
TEL001
Programme
ISG - Technology Enhanced Learning (TEL)
Project Manager
Laura Bell
Project Sponsor
Bryan MacGregor
Current Stage
Close
Status
Closed
Start Date
29-Nov-2012
Planning Date
n/a
Delivery Date
n/a
Close Date
01-Aug-2013
Programme Priority
2
Overall Priority
Normal
Category
Compliance