Organisation
Work/Task Breakdown
Planning - 14/12/12 Analysis of Upgrade and De-Provisioning - PPAR by end of January Design, Build and Test PPDR/BR - by end of March Acceptance (ASOR) - by end of May Delivery and Closure - by mid-June
See PebblePad-Upgrade-Draft-Plan-v2 in the Estimation Log
Resources Skills and Cost Applications - 29 days three point estimate TEL - 21.4 days USD/ITI/Other - 21.6 days
Contingency - 10 days for Apps
See Three Point Estimate in the Estimation Log