Organisation

 

Work/Task Breakdown

Planning - 14/12/12 Analysis of Upgrade and De-Provisioning - PPAR by end of January Design, Build and Test PPDR/BR - by end of March Acceptance (ASOR) - by end of May Delivery and Closure - by mid-June

 

See PebblePad-Upgrade-Draft-Plan-v2 in the Estimation Log

 

Resources Skills and Cost Applications - 29 days three point estimate TEL - 21.4 days USD/ITI/Other - 21.6 days

Contingency - 10 days for Apps

See Three Point Estimate in the Estimation Log

 

 

Project Info

Project
PebblePad Upgrade 2013
Code
TEL001
Programme
ISG - Technology Enhanced Learning (TEL)
Project Manager
Laura Bell
Project Sponsor
Bryan MacGregor
Current Stage
Close
Status
Closed
Start Date
29-Nov-2012
Planning Date
n/a
Delivery Date
n/a
Close Date
01-Aug-2013
Programme Priority
2
Overall Priority
Normal
Category
Compliance