Report for May 2013

Report Date
May 2013

Achievements in Last Period

  • Integration testing partially completed; Pebblepad to complete final link of new Eugex feed before testing can complete
  • Discussions with schools on current position
  • Training material completed

Issues

The project is amber, as, following discussions with College representatives, the recommendation is to defer deployment to later in June.

The project is working through some current topics; none of which are expected to delay deployment:

  • There are some current connection issues with Pebblepad which affect the set up of groups to individual workspaces; it is anticipated that these will be resolved prior to, or shortly after deployment. A manual alternative is available.
  • The new version has some accessibility issues; following discussion with the disability officer, the current approach is agreed. An Equality Impact Assessment is being completed.
  • Pebblepad confirmed "Turn It In" functionality will not be included in July release. This impacts schools which submit assessments via Pebblepad. The schools have indicated that they will either (a) seek an alternative service or (b) identify manual alternatives.
  • Following discussion with the Project Sponsor and Fraser Muir, it has been agreed that the new upgrade should be deployed in later June.

Next Period

  • Complete final communications to schools
  • Sign off User Acceptance Testing
  • Deploy Pebblepad v3

 

 

Target dateTitle
31-May-2013User Acceptance (ASOR)
14-Jun-2013Delivery
21-Jun-2013Deployment Sign-Off
28-Jun-2013Closure

 

 

 

 

Project Status
RAG Status
Time
RED
Cost
AMBER
Scope
GREEN
Overall
AMBER
Change Status
Activity
Approved budget
34.0 days
Activity this month
3.3 days
Activity this year
30.5 days
Activity to date
30.6 days
Estimate to complete current year
4.2 days
Estimate to complete future years
0.0 days

Project Info

Project
PebblePad Upgrade 2013
Code
TEL001
Programme
ISG - Technology Enhanced Learning (TEL)
Project Manager
Laura Bell
Project Sponsor
Bryan MacGregor
Current Stage
Close
Status
Closed
Start Date
29-Nov-2012
Planning Date
n/a
Delivery Date
n/a
Close Date
01-Aug-2013
Programme Priority
2
Overall Priority
Normal
Category
Compliance