Report for June 2013

Report Date
June 2013

Achievements in Last Period

  • Completed final communications to schools and agreed "go" decision
  • Accessibility issues reviewed and resolved
  • User Acceptance Testing signed off (excluding Eugex data feed)
  • Deploy Pebblepad v3 (excluding Eugex data feed)

Issues

  • Due to ongoing connection issues with Pebblepad, and issues with the Eugex Test data, the project was unable to conclude testing of the new eugex data feed prior to deployment. This is required for schools to set up workspaces and is not required until later in July. Therefore, this will be deployed once testing has concluded (target is by 10/7).
  • A number of issues occurred during the deployment which required some tasks to be repeated with Pebble Learning. Therefore, the project cost is Amber as this may require some additional budget to cover these issues and conclude deployment of the Eugex data feed (2-3 days).

Next Period

  • Complete deployment of Eugex data feed to Pebble Learning
  • Sign off Deployment
  • Close Project

 

 

 

Project Status
RAG Status
Time
GREEN
Cost
RED
Scope
GREEN
Overall
BLUE
Change Status
Activity
Approved budget
34.0 days
Activity this month
7.8 days
Activity this year
35.0 days
Activity to date
35.0 days
Estimate to complete current year
1.5 days
Estimate to complete future years
0.0 days

Project Info

Project
PebblePad Upgrade 2013
Code
TEL001
Programme
ISG - Technology Enhanced Learning (TEL)
Project Manager
Laura Bell
Project Sponsor
Bryan MacGregor
Current Stage
Close
Status
Closed
Start Date
29-Nov-2012
Planning Date
n/a
Delivery Date
n/a
Close Date
01-Aug-2013
Programme Priority
2
Overall Priority
Normal
Category
Compliance