Acceptance Tests and Outcomes

UAT Scenarios

User test plans as follows:

Moodle - https://www.projects.ed.ac.uk/webfm_send/1981

Learn - https://www.projects.ed.ac.uk/webfm_send/1979

MyEd - https://www.projects.ed.ac.uk/webfm_send/1980

Eugex - https://www.projects.ed.ac.uk/webfm_send/1982

Open Issues

 

Any issues identified during UAT must be added to the Test Log. Please summarise or insert a copy of any open issues from the JIRA Test Log. It may be agreed that UAT can be signed off while some issues remain open please provide details of the UAT impact of each open issue.

 

 

BRD Ref

JIRA Test Log Ref

Issue Summary

Impact on UAT Sign Off

TEL001 - 1Course group provisioning maintained from EUCLID - due to issues with Pebble Learning set up and issues with the Eugex test environment, this  functionality was not able to be tested prior to deployment.Agreed at UAT that the testing and deployment of this functionality would be completed post upgrade and pre closure.

 8

 n/a

New IDM provisioning - as Pebble Learning are not using the IDM feed to maintain accounts, it was agreed that this process would be completed manually. Due to the volume of issues this was not completed prior to deployment.TEL team to finalise process and book a date for completion pre closure. Removal of accounts will take place post closure.

 2

 n/a

IS Helpline to become first contactThe approach to service support is still to be defined by USD and therefore this may no longer be required. Action plan to be agreed with USD/ IS Helpline pre closure.

 

Link to updated JIRA Test Log

Document Sign Off

Please add other signatories where required

 

 

Project Manager

Laura bell

21/6

Project Sponsor

Mark Wetton

21/6

Business Analyst

Mark Findlay

21/6

Add other signatories here

 

 

 

Project Info

Project
PebblePad Upgrade 2013
Code
TEL001
Programme
ISG - Technology Enhanced Learning (TEL)
Project Manager
Laura Bell
Project Sponsor
Bryan MacGregor
Current Stage
Close
Status
Closed
Start Date
29-Nov-2012
Planning Date
n/a
Delivery Date
n/a
Close Date
01-Aug-2013
Programme Priority
2
Overall Priority
Normal
Category