Organisation
Work/Task Breakdown
Task | Deliverable | Owner |
Project Management | Project authorisation, Brief and Project documents. Communication and coordination with stakeholders. | Franck Bergeret |
Build It | Technical Architecture Document Install databases Test and Live Data conversion Data migration Package and deploy solution | IS Dev Tech IS Dev Tech/Speedwell IS Dev Tech/Speedwell IS Dev Tech/Speedwell IS Dev Tech/Desktop Services |
Check It | Plan Test Write test plan Test Databases Test Migrated data Support for testing | Franck Bergeret FB MVM end users + FB to QA MVM end users + FB to QA MVM end users + FB to QA IS Dev Tech/Speedwell |
Document | Operational Document (OD), handover to Production
Service Level Agreement (SLA) | IS Dev Tech IS App Management |
Release | Deploy Live database with data migrated Package and deploy Live solution Check Live software/migrated data | IS Dev Tech/Speedwell
Dev Tech/ Desktop Services MVM end users/senior user |
Close It | Closure Review | Franck Bergeret |
Resources Skills and Cost
The project is to be approved based on an estimate of 35 days for IS Apps.
Task | Days Allocation | Resource |
Project Management, Planning, review, communication | 6.5 days 0.5 day | Franck Bergeret Director office |
To document, install & configure Test and Live servers and databases. To manage the conversion and migration with Speedwell on Test and Live. To work on the packaging of the solution.To handover to Production. Contingency, unplanned tasks | 20.5 days
2 days | IS Dev Tech |
Handover and write SLA Review documentation | 2 days 0.5 day | IS Apps Man IS Tech Man |
To provide testing guidelines, help with test plan | 2 day | Project team |
Closure | 1 day | Franck Bergeret |