Report for September 2012

Report Date
September 2012

 

Achievements in Last Period

  • Brief signed off
  • TAD reviewed
  • First two Speedwell softwares installed and linked OK with the Test database on the new shared server

Issues

N/A

Next Steps  

  • Data conversion and migration may not be required as there is an import facility in the new version of the third software due end Oct. Business Lead to confirm and PM to update project scope accordingly.
  • A new version of the third software will be released end Oct 12. The UAT can only start after that date. 
  • To agree new dates once new project scope confirmed by Business Lead.

 

Target dateTitle
26-Sep-2012Convert and migrate data into 3 Test databases
26-Oct-2012Check data migrated/software in Test
02-Nov-2012ASOR sign off test
12-Nov-2012Convert and Migrate data in the 3 Live databases
19-Nov-2012Package and deploy Live to desktop
26-Nov-2012Deployment sign off DSOR
12-Dec-2012Closure

 

Project Status
RAG Status
Overall
GREEN
Change Status
Activity
Approved budget
35.0 days
Activity this month
8.0 days
Activity this year
13.6 days
Activity to date
13.6 days
Estimate to complete current year
20.9 days
Estimate to complete future years
0.0 days

Project Info

Project
Speedwell database hosting
Code
TEL002
Programme
ISG - Technology Enhanced Learning (TEL)
Project Manager
Franck Bergeret
Project Sponsor
David Williamson
Current Stage
Close
Status
Closed
Start Date
06-Aug-2012
Planning Date
n/a
Delivery Date
n/a
Close Date
14-Jun-2013