Report for September 2012
- Report Date
- September 2012
Achievements in Last Period
- Brief signed off
- TAD reviewed
- First two Speedwell softwares installed and linked OK with the Test database on the new shared server
Issues
N/A
Next Steps
- Data conversion and migration may not be required as there is an import facility in the new version of the third software due end Oct. Business Lead to confirm and PM to update project scope accordingly.
- A new version of the third software will be released end Oct 12. The UAT can only start after that date.
- To agree new dates once new project scope confirmed by Business Lead.
Target date | Title |
---|---|
26-Sep-2012 | Convert and migrate data into 3 Test databases |
26-Oct-2012 | Check data migrated/software in Test |
02-Nov-2012 | ASOR sign off test |
12-Nov-2012 | Convert and Migrate data in the 3 Live databases |
19-Nov-2012 | Package and deploy Live to desktop |
26-Nov-2012 | Deployment sign off DSOR |
12-Dec-2012 | Closure |
- Approved budget
- 35.0 days
- Activity this month
- 8.0 days
- Activity this year
- 13.6 days
- Activity to date
- 13.6 days
- Estimate to complete current year
- 20.9 days
- Estimate to complete future years
- 0.0 days