Report for October 2012
- Report Date
- October 2012
Achievements in Last Period
-Completed deployment and testing of the 1st two Speedwell softwares, using the Test database on the new shared server for two users.
-Completed 1st draft of the Test Plan.
Issues
Delay by the supplier in releasing the new version of the third required software expected early Nov (was 31 Oct). This will cause delay in the planned UAT, no date set as of 6/11. Risk managed accordingly as per hard deadline for go live set to 10th Dec by Business Lead. RAG status set to Red.
Next Steps
- Deploy third software once new version has been received from supplier
- Complete UAT
Target date | Title |
---|---|
14-Nov-2012 | UAT - Check software in Test signed off |
24-Nov-2012 | ASOR sign off test |
29-Nov-2012 | Package and deploy Live to desktop |
06-Dec-2012 | Deployment sign off DSOR |
19-Dec-2012 | Closure |
- Approved budget
- 35.0 days
- Activity this month
- 2.2 days
- Activity this year
- 16.0 days
- Activity to date
- 15.8 days
- Estimate to complete current year
- 18.0 days
- Estimate to complete future years
- 0.0 days