Report for October 2012

Report Date
October 2012

Achievements in Last Period

-Completed deployment and testing of the 1st two Speedwell softwares, using the Test database on the new shared server for two users.

-Completed 1st draft of the Test Plan.

Issues

Delay by the supplier in releasing the new version of the third required software expected early Nov (was 31 Oct). This will cause delay in the planned UAT, no date set as of 6/11. Risk managed accordingly as per hard deadline for go live set to 10th Dec by Business Lead.  RAG status set to Red.

Next Steps

- Deploy third software once new version has been received from supplier

- Complete UAT 

 

 

Target dateTitle
14-Nov-2012UAT - Check software in Test signed off
24-Nov-2012ASOR sign off test
29-Nov-2012Package and deploy Live to desktop
06-Dec-2012Deployment sign off DSOR
19-Dec-2012Closure

 

 

Project Status
Activity
Approved budget
35.0 days
Activity this month
2.2 days
Activity this year
16.0 days
Activity to date
15.8 days
Estimate to complete current year
18.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Speedwell database hosting
Code
TEL002
Programme
ISG - Technology Enhanced Learning (TEL)
Project Manager
Franck Bergeret
Project Sponsor
David Williamson
Current Stage
Close
Status
Closed
Start Date
06-Aug-2012
Planning Date
n/a
Delivery Date
n/a
Close Date
14-Jun-2013