Report for November 2012

Report Date
November 2012

 

Achievements in Last Period

  • Completed the Test Plan.

Issues

  • Delay by the supplier in releasing the new version of the third required software expected early Jan (was early Nov). This will cause delay in the planned UAT: now planned w/b 28/1/13 after the January exams. Agreed with stakeholders to keep using the current software versions for the Januray exams and deploy the new software version on the new hosted database in Feb 13. No impact on budget.

Next Steps

  • Deploy third software once new version has been received from supplier
  • Complete UAT 
  • Deploy to Live

 

15-Jan-2013UAT - Check software in Test signed off
06-Feb-2013ASOR sign off test
13-Feb-2013Package and deploy Live to desktop
18-Feb-2013Deployment sign off DSOR
01-Mar-2013Closure

 

Project Status
RAG Status
Overall
AMBER
Change Status
Activity
Approved budget
35.0 days
Activity this month
1.5 days
Activity this year
18.4 days
Activity to date
18.4 days
Estimate to complete current year
16.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Speedwell database hosting
Code
TEL002
Programme
ISG - Technology Enhanced Learning (TEL)
Project Manager
Franck Bergeret
Project Sponsor
David Williamson
Current Stage
Close
Status
Closed
Start Date
06-Aug-2012
Planning Date
n/a
Delivery Date
n/a
Close Date
14-Jun-2013