Report for January 2013

Report Date
January 2013

 

Achievements in Last Period

  • N/A

Issues

  • Delay by the supplier in releasing the new version of the third required software. It was only released on 24/1 (was last expected early Jan). This will cause delay in the planned UAT by MVM: now planned for 21/2/13. Agreed with stakeholders. No impact on budget.

Next Steps

  • Package and deploy third software to MVM users' machines  
  • Complete UAT 
  • Install Live database on shared server
  • Package and deploy the 3 softwares to Live

 

 

Target dateTitle
01-Mar-2013ASOR sign off test
14-Mar-2013Package and deploy Live to desktop
19-Mar-2013Deployment sign off DSOR
01-Apr-2013Closure

 

Project Status
RAG Status
Overall
GREEN
Change Status
Activity
Approved budget
35.0 days
Activity this month
1.9 days
Activity this year
20.4 days
Activity to date
20.4 days
Estimate to complete current year
14.4 days
Estimate to complete future years
0.0 days

Project Info

Project
Speedwell database hosting
Code
TEL002
Programme
ISG - Technology Enhanced Learning (TEL)
Project Manager
Franck Bergeret
Project Sponsor
David Williamson
Current Stage
Close
Status
Closed
Start Date
06-Aug-2012
Planning Date
n/a
Delivery Date
n/a
Close Date
14-Jun-2013