Report for January 2013
- Report Date
- January 2013
Achievements in Last Period
- N/A
Issues
- Delay by the supplier in releasing the new version of the third required software. It was only released on 24/1 (was last expected early Jan). This will cause delay in the planned UAT by MVM: now planned for 21/2/13. Agreed with stakeholders. No impact on budget.
Next Steps
- Package and deploy third software to MVM users' machines
- Complete UAT
- Install Live database on shared server
- Package and deploy the 3 softwares to Live
Target date | Title |
---|---|
01-Mar-2013 | ASOR sign off test |
14-Mar-2013 | Package and deploy Live to desktop |
19-Mar-2013 | Deployment sign off DSOR |
01-Apr-2013 | Closure |
- Approved budget
- 35.0 days
- Activity this month
- 1.9 days
- Activity this year
- 20.4 days
- Activity to date
- 20.4 days
- Estimate to complete current year
- 14.4 days
- Estimate to complete future years
- 0.0 days