Report for February 2013
- Report Date
- February 2013
Achievements in Last Period
- UAT completed and signed off.
Issues
- N/A
Next Steps
- ASOR sign off once handover completed between Production & Dev Tech
- Install Live databases on shared server
- Deploy to Live
01-Mar-2013 | ASOR sign off acceptance |
14-Mar-2013 | Deploy Live |
19-Mar-2013 | Deployment sign off DSOR |
01-Apr-2013 | Closure |
- Approved budget
- 35.0 days
- Activity this month
- 5.0 days
- Activity this year
- 25.4 days
- Activity to date
- 25.4 days
- Estimate to complete current year
- 10.8 days
- Estimate to complete future years
- 0.0 days