Report for March 2013

Report Date
March 2013

 

Achievements in Last Period

  • Delivery started

Issues

  • The installation of Speedwell has failed on one machine, so deployment not complete. Set status as Amber as we need to restate the compeltion date and closure.

Next Steps

  • Complete Deployment to Live

 

 

14-Mar-2013Deploy Live
19-Mar-2013Deployment sign off DSOR
01-Apr-2013Closure

 

Project Status
RAG Status
Time
AMBER
Cost
GREEN
Scope
GREEN
Overall
AMBER
Change Status
Activity
Approved budget
35.0 days
Activity this month
5.0 days
Activity this year
30.0 days
Activity to date
30.0 days
Estimate to complete current year
6.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Speedwell database hosting
Code
TEL002
Programme
ISG - Technology Enhanced Learning (TEL)
Project Manager
Franck Bergeret
Project Sponsor
David Williamson
Current Stage
Close
Status
Closed
Start Date
06-Aug-2012
Planning Date
n/a
Delivery Date
n/a
Close Date
14-Jun-2013