Achievements in Last Period
- Deployment Sign Off (DSOR) completed
- Days for annual maintenance agreed between IS Apps Production and MVM Business Lead
- Remaining test to be completed post DSOR: test that the supplier Speedwell has access to the database for future maintenance. Delayed due to ITI work priority. This will be managed as a support call.
Issues
N/A
Next Steps
- Closure: report has been sent to stakeholders.
06-Jun-2013 | Closure |
- Approved budget
- 35.0 days
- Activity this month
- 1.3 days
- Activity this year
- 33.1 days
- Activity to date
- 33.1 days
- Estimate to complete current year
- 1.0 day
- Estimate to complete future years
- 0.0 days