Approval

Approval Record

 

 

Check List Item (ToR Reference)

Quality Criteria

Complete Y/N

Reviewed By

Scope, Objectives and Deliverables (2.2, 2.3)

  • Boundaries for project clearly identified. 
  • Objectives and deliverables clearly identified.

Y

Fraser Muir, David Watters, Michael Holmes and Andrew McFarlane

Milestones (2.4)

  • All milestones identified

Y

David Smyth

Fraser Muir, David Watters, Michael Holmes and Andrew McFarlane

Costs (3.1.1)

  • Five year costs identified including any recurrent costs 

Y

Fraser Muir, David Watters, Michael Holmes and Andrew McFarlane

Funding

  • Sources of funding identified
  • Funding secured
  • Any special payment terms identified

Y

Fraser Muir, David Watters, Michael Holmes and Andrew McFarlane

Benefits (3.1.4)

  • Five year benefits identified and realistic.
  • Realisation approach stated

Y

Fraser Muir, David Watters, Michael Holmes and Andrew McFarlane

Project and Service Impacts (3.3)

  • Impacts identified
  • Project/Service management aware

Y

Sheila Fraser

Risk (3.4)

  • Risk Register complete
  • Highest Impact/Probability risks identified
  • Clear and sensible Risk Management  Approach

Y

Fraser Muir, David Watters, Michael Holmes and Andrew McFarlane

Roles and Stakeholders (4.1)

  • Project Roles identified
  • Evidence of appropriate Project Sponsor commitment
  • Evidence of IS awareness and commitment
  • Evidence of customer engagement

Y

Fraser Muir, David Watters, Michael Holmes and Andrew McFarlane

Resource Estimate (4.3.1)

  • Credible estimate completed with appropriate engagement of all parties
  • Assumptions clearly stated
  • Required actions taken where estimate exceeds original project proposal estimate

Y

IS Apps contributors to estimates: Tomasz Pogoda, Andrew McFarlane, Brian Denholm, David Watters, Neil Grant, Ron McLeod

SACS: Rachel Lacaille

Project Plan (4.4)

  • Project plan exists and is credible
  • Evidence that plan will be used to drive the project

Y

PM

 

Approval Record

 

TOR Raised By

Franck Bergeret

Date Raised

14/11/12

Date TOR Reviewed

16/11/12 by Fraser Muir, David Watters, Michael Holmes and Andrew McFarlane

Date TOR Approved

Date TOR approved

 

Project Info

Project
Extension of SMART to HSS with Enhancements
Code
TEL003
Programme
CAHSS Portfolio Projects
Project Manager
Maurice Franceschi
Project Sponsor
Fraser Muir
Current Stage
Close
Status
Closed
Start Date
22-Oct-2012
Planning Date
n/a
Delivery Date
n/a
Close Date
09-Aug-2013
Category
Discretionary