Project Activity - w/c 10th June, 17th June, 24th June, 1st July, 8th July
W/c 10th June
- Accessibility testing completed - no issues identified
- Due to issues with eugex test feed, deployment date revised to 26th June; revised due to issues with Eugex test feed
- Service outage agreed with Calum MacLean and Infinite Users
W/c 17th June
- UAT Testing completed; JIRAs raised and rebuild completed
- Issues with Eugex Test feed ongoing; deployment date had to be revised
W/c 24th June
- Issue: change to how email notification process required; agreed with Project sponsor that this should be in scope
- Eugex Test feed rebuilt and now able to complete 2nd stage of testing (awaiting record test)
W/c 1st July
- 2nd stage of UAT completed: Awaiting record testing completed
- Rebuild of bugs completed and retested
- Deployment checklist completed - issue identified with quality of TAD; to be revised
- Acceptance sign off completed
W/c 8th July
- ODL applications deployed on 10th July; issue identified with publication of channel to be completed w/c 15th July
- TAD revised - significantly more work than anticipated (6h)