Project Activity - w/c 10th June, 17th June, 24th June, 1st July, 8th July

W/c 10th June

  • Accessibility testing completed - no issues identified
  • Due to issues with eugex test feed, deployment date revised to 26th June; revised due to issues with Eugex test feed
  • Service outage agreed with Calum MacLean and Infinite Users

W/c 17th June

  • UAT Testing completed; JIRAs raised and rebuild completed
  • Issues with Eugex Test feed ongoing; deployment date had to be revised

W/c 24th June

  • Issue: change to how email notification process required; agreed with Project sponsor that this should be in scope
  • Eugex Test feed rebuilt and now able to complete 2nd stage of testing (awaiting record test)

 

W/c 1st July

  • 2nd stage of UAT completed: Awaiting record testing completed
  • Rebuild of bugs completed and retested
  • Deployment checklist completed - issue identified with quality of TAD; to be revised
  • Acceptance sign off completed

 

W/c 8th July

  • ODL applications deployed on 10th July; issue identified with publication of channel to be completed w/c 15th July
  • TAD revised - significantly more work than anticipated (6h)