Project Activity - w/c 15/7, 22/7, 29/7
W/c 15th July
- Confirmation from Card Services that Applications views now working following "publishing" procedure from Web Integration
- Card Services completed a test in LIVE using an ODL student who is also a member of staff.
- Issue identified to show that application not working as anticipated in LIVE; as developer on Leave, resolution delayed until w/c 22/7
- Budget issues discussed with Programme manager who confirmed that, as within 10%, this did not require to be escalated
W/c 22nd July
- Review with Developer, Apps Mgt and Dev Tech identified the issue and resolved it (issue to do with database configuration)
- Retested and confirmed correct by Card Services
- DSOR sign off completed on 26/7
- Budget issues discussed again with Programme manager who agreed that budget change should be highlighted; Maurice F discussed with Bryan McGregor. Programme Manager confirmed closure should go ahead.
- Project Closure report drafted and issued for sign off.
W/c 29th July