Work/Task Breakdown
Task | Deliverable | Owner |
Project Management | Project authorisation, Brief and Project documents. Communication and coordination with stakeholders. | Project Services |
Build It | Review of Systems Design and Application in Development environment (including documentation) following MyEd upgrade | Dev Team |
Deploy Image upload and management application to Test environment | Dev Tech | |
Check It | Complete Integration testing, including integration with MyEd following upgrade Complete UAT | Apps Mgt, Service Mgt Card Services |
Document | Complete integration documentation Complete service management documentation | Apps Mgt Service Mgt |
Release | Complete deployment checks Deploy Image upload and management application Deploy MyEd portlet Handover of Applications to support | Dev Tech Dev Tech, Apps Mgt Apps Mgt, Service Mgt Apps Mgt |
Close It | Closure Review | Project Services |
Resources Skills and Cost
The project currently assumes 20 days effort which includes 1 day of effort for Service Management. A summary of effort by team is as follows:
Project Services (Project management, planning, etc.) - 5.3 days
Development Team (Confirm build, complete systems testing) - 5.9 days
Development Technical Team (deploy to test and live environment) - 0.8 days
Application Mgt (Integration testing) - 3.9 days
Service Mgt (testing with MyEd channel) - 1 day
Meetings/ Sign Offs/ Closure - 3.1 days
A breakdown of resources and effort is provided in the Three Point Estimate.