Organisation

 

Work/Task Breakdown

 

Task

Deliverable

Owner

Project Management

Project authorisation, Brief and Project documents. Communication and coordination with stakeholders.

Project Services

Build It

Review of Systems Design and Application in Development environment (including documentation)  following MyEd upgradeDev Team

Deploy Image upload and management application to Test environment

Dev Tech
Check It

Complete Integration testing, including integration with MyEd following upgrade

Complete UAT

Apps Mgt, Service Mgt

Card Services

Document

Complete integration documentation

Complete service management documentation

Apps Mgt

Service Mgt

Release

Complete deployment checks

Deploy Image upload and management application

Deploy MyEd portlet

Handover of Applications to support

Dev Tech

Dev Tech, Apps Mgt

Apps Mgt, Service Mgt

Apps Mgt

Close It

Closure Review

Project Services

Resources Skills and Cost

 

The project currently assumes 20 days effort which includes 1 day of effort for Service Management. A summary of effort by team is as follows:

Project Services (Project management, planning, etc.) - 5.3 days

Development Team (Confirm build, complete systems testing) - 5.9 days

Development Technical Team (deploy to test and live environment) - 0.8 days

Application Mgt (Integration testing) - 3.9 days

Service Mgt (testing with MyEd channel) - 1 day

Meetings/ Sign Offs/ Closure - 3.1 days

A breakdown of resources and effort is provided in the Three Point Estimate.