Report for May 2013

Report Date
May 2013

Achievements in Last Period

  • The project was due to complete Integration and acceptance testing in the last period.
  • Due to infrastructure/ budget issues, and key staff absence, milestones were revised
  • Infrastructure changes implemented; applications stable
  • Stage 1 of integration testing complete
  • Budget re-estimated and revised

Issues

  • New test data issues have meant that stage 2 of the integration testing cannot complete; a rebuild of the data stream from SITS to Eugex is underway to try to resolve issue
  • This issue places deployment date of 17/6 at risk.

Next Period

  • Complete Integration and Acceptance Testing
  • Deploy to Live

 

 

Target dateTitle
07-Jun-2013PPIR Phase 2 (Peer Project Integration Review)
12-Jun-2013ASOR Phase 2 (Acceptance Sign Off Review)
17-Jun-2013Deploy to Live
28-Jun-2013DSOR Phase 2 Sign off (Deployment Sign off review)
05-Jul-2013Project Closure

 

 

 

Project Status
RAG Status
Time
RED
Cost
GREEN
Scope
GREEN
Overall
RED
Change Status
Activity
Approved budget
38.0 days
Activity this month
2.8 days
Activity this year
26.5 days
Activity to date
26.5 days
Estimate to complete current year
11.2 days
Estimate to complete future years
0.0 days