Report for May 2013
- Report Date
- May 2013
Achievements in Last Period
- The project was due to complete Integration and acceptance testing in the last period.
- Due to infrastructure/ budget issues, and key staff absence, milestones were revised
- Infrastructure changes implemented; applications stable
- Stage 1 of integration testing complete
- Budget re-estimated and revised
Issues
- New test data issues have meant that stage 2 of the integration testing cannot complete; a rebuild of the data stream from SITS to Eugex is underway to try to resolve issue
- This issue places deployment date of 17/6 at risk.
Next Period
- Complete Integration and Acceptance Testing
- Deploy to Live
Target date | Title |
---|---|
07-Jun-2013 | PPIR Phase 2 (Peer Project Integration Review) |
12-Jun-2013 | ASOR Phase 2 (Acceptance Sign Off Review) |
17-Jun-2013 | Deploy to Live |
28-Jun-2013 | DSOR Phase 2 Sign off (Deployment Sign off review) |
05-Jul-2013 | Project Closure |
- Approved budget
- 38.0 days
- Activity this month
- 2.8 days
- Activity this year
- 26.5 days
- Activity to date
- 26.5 days
- Estimate to complete current year
- 11.2 days
- Estimate to complete future years
- 0.0 days