Report for June 2013
- Report Date
- June 2013
Achievements in Last Period
- The project was due to complete acceptance testing and deploy in the last period.
- Due to test infrastructure issues, the dates were revised.
Issues
- The deployment requires Dev Tech resource - this is currently being finalised.
Next Period
- Complete Acceptance sign off
- Deploy to Live
- Close project
Target date | Title |
---|---|
08-Jul-2013 | ASOR Phase 2 (Acceptance Sign Off Review) |
10-Jul-2013 | Deploy to Live |
22-Jul-2013 | DSOR Phase 2 Sign off (Deployment Sign off review) |
26-Jul-2013 | Project Closure |
- Approved budget
- 38.0 days
- Activity this month
- 9.3 days
- Activity this year
- 35.4 days
- Activity to date
- 33.1 days
- Estimate to complete current year
- 4.2 days
- Estimate to complete future years
- 0.0 days