Report for June 2013

Report Date
June 2013

Achievements in Last Period

  • The project was due to complete acceptance testing and deploy in the last period.
  • Due to test infrastructure issues, the dates were revised.

Issues

  • The deployment requires Dev Tech resource - this is currently being finalised.

Next Period

  • Complete Acceptance sign off
  • Deploy to Live
  • Close project

 

 

Target dateTitle
08-Jul-2013ASOR Phase 2 (Acceptance Sign Off Review)
10-Jul-2013Deploy to Live
22-Jul-2013DSOR Phase 2 Sign off (Deployment Sign off review)
26-Jul-2013Project Closure

 

Project Status
RAG Status
Time
AMBER
Cost
AMBER
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
38.0 days
Activity this month
9.3 days
Activity this year
35.4 days
Activity to date
33.1 days
Estimate to complete current year
4.2 days
Estimate to complete future years
0.0 days