April 2015

Report Date
April 2015

Top Hat have been awarded the contract. However, the T&C's now have to be written up.

The SLA from Top Hat was unsatisfactory, so an SLA will be drafted by UoE.

Achievements in Last Period

  • write up T&C's and agree contract - not completed
  • write an SLA - not completed

Issues

  • no issues at this stage
  • no amber or red risks

Next Steps

  • write up T&C's and agree contract
  • write an SLA

Milestones

 

29-May-2015Sign Contract
12-Jun-2015Closure

 

Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
55.0 days
Activity this month
1.0 day
Activity this year
59.0 days
Activity to date
59.0 days
Estimate to complete current year
1.0 day
Estimate to complete future years
0.0 days