May 2015

Report Date
May 2015

There have been a series of teleconferences to discuss and resolve a number of contract points.

The end is in sight, and we hope that a teleconference on 2nd June will be out last, and that then the contract can be completed. The length of this negotiation has meant the budget has been exceeded by a couple of days.

 

Achievements in Last Period

  • write up T&C's and agree contract - not completed
  • write an SLA - not completed

Issues

  • no issues at this stage
  • no amber or red risks

Next Steps

  • write up T&C's and agree contract
  • write an SLA

Milestones

 

29-May-2015Sign Contract
12-Jun-2015Closure

 

Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
60.0 days
Activity this month
1.0 day
Activity this year
31.0 days
Activity to date
60.0 days
Estimate to complete current year
1.0 day
Estimate to complete future years
0.0 days