June 2015

Report Date
June 2015

 

A contract has been agreed with Top Hat. Contract has been sent for printing and subsequent signing.

 

 

Achievements in Last Period

  • write up T&C's and agree contract - done
  • write an SLA - done

Issues

  • no issues at this stage
  • no amber or red risks

Next Steps

  • closure w/c 29th June

Milestones

 

1-Jul-2015Closure

 

Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
BLUE
Change Status
Activity
Approved budget
63.0 days
Activity this month
1.0 day
Activity this year
33.0 days
Activity to date
63.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days