Report for June 2015

Report Date
June 2015

Achievements this period

  • Building blocks under development
  • Additional effort assigned to refactor build work
  • Database performance tests undertaken in DEV
  • Peer reviewer assigned

Issues

  • Currently planned effort exceeds agreed  budget.

Next Steps

  • Build stage to complete
  • Build review to be held
  • Deploy to TEST
  • Performance test to be undertaken in TEST

 

Milestones

 

New 
6-Jul-2015Build review stage 2
30-Jul-2015Accept stage 2
03-Aug-2015Delivery
18-Aug-2015Deployment sign-off review
31-Aug-2015Closure

 

The project RAG status is GREEN

Programme Manager : due to the high number of risks needing reviewed, project status set to AMBER.

Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
AMBER
Change Status
Activity
Approved budget
185.0 days
Activity this month
11.0 days
Activity this year
142.0 days
Activity to date
142.0 days
Estimate to complete current year
41.0 days
Estimate to complete future years
14.0 days