Report for June 2015
- Report Date
- June 2015
Achievements this period
- Building blocks under development
- Additional effort assigned to refactor build work
- Database performance tests undertaken in DEV
- Peer reviewer assigned
Issues
- Currently planned effort exceeds agreed budget.
Next Steps
- Build stage to complete
- Build review to be held
- Deploy to TEST
- Performance test to be undertaken in TEST
Milestones
New | |
6-Jul-2015 | Build review stage 2 |
30-Jul-2015 | Accept stage 2 |
03-Aug-2015 | Delivery |
18-Aug-2015 | Deployment sign-off review |
31-Aug-2015 | Closure |
The project RAG status is GREEN
Programme Manager : due to the high number of risks needing reviewed, project status set to AMBER.
- Approved budget
- 185.0 days
- Activity this month
- 11.0 days
- Activity this year
- 142.0 days
- Activity to date
- 142.0 days
- Estimate to complete current year
- 41.0 days
- Estimate to complete future years
- 14.0 days