Report for July 2015 - draft

Report Date
July 2015

Achievements this period

  • Build sign off complete
  • Deployment to TEST complete
  • UAT underway

Issues

  • Limited time to complete UAT and LIVE deployment
  • SDD to be completed

Next Steps

  • Performance test to be undertaken in TEST
  • Acceptance review to be signed off
  • Live deployment to take place w/c 3 August
  • SDD to be completed

 

Milestones

 

New 
30-Jul-2015Accept stage 2
03-Aug-2015Delivery
18-Aug-2015Deployment sign-off review
31-Aug-2015Closure

 

The project RAG status is GREEN

 

Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days