Report for March 2015

Report Date
March 2015

Achievements this period

  • Analysis milestone signed off
  • Business requirements updated and signed off
  • Design drafted and peer reviewed.

Issues

No issues

Next Steps

  • Design to be signed off
  • Project to be re-estimated as part of design signoff
  • Build stage to commence
  • Build review to be held
  • Acceptance stage to commence

 

Milestones

 

07-Apr-2015Design Signoff Stage 2
23-Apr-2015Build stage 2
26-May-2015Accept stage 2
08-Jun-2015Delivery
22-Jun-2015Deployment sign-off review
07-Jul-2015Closure
 

The project RAG status is GREEN

Project Status
RAG Status
Time
AMBER
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
200.0 days
Activity this month
8.0 days
Activity this year
112.0 days
Activity to date
113.0 days
Estimate to complete current year
87.0 days
Estimate to complete future years
0.0 days