The second phase of TREE development aims to develop the tool further, meeting more of the initial requirements gathered and reengaging with the users to see if they have further requirements now that the tool is live.
The requirements gathering and prioritisation processes are now complete and we are in the 1st iteration of the build focusing on expanding content within TREE. This stage is due to be complete on the 6th of January although the additional content will continue to be gathered throughout all the iterations.
Current project status
Report Date | RAG | Budget | Effort Completed | Effort to complete |
---|---|---|---|---|
December 2014 | BLUE | 0.0 days | 0.0 days | 0.0 |