August 2015
- Report Date
- August 2015
The service had a soft launch on 2nd July and once contract signed and some fixes made - formally launched on 28th July.
Achievements in Last Period
- SSO for applications from TopHat pending in July needs checked - done
- follow up on the rooms identified as at risk for insufficient capacity - done
- follow up on NHS staff using Top Hat. - done - no further action here. Paul Clark informed.
- decommission clickers system - done. SOftware removed from managed desktop.
Issues
- none
- no amber or red risks
Next Steps
- closure
Milestones
09-Sep-2015 | Project Closure |
- Approved budget
- 30.0 days
- Activity this month
- 0.5 days
- Activity this year
- 0.5 days
- Activity to date
- 21.0 days
- Estimate to complete current year
- 1.0 day
- Estimate to complete future years
- 0.0 days