August 2015

Report Date
August 2015

The service had a soft launch on 2nd July and  once contract signed and some fixes made - formally launched on 28th July.

Achievements in Last Period

  • SSO for applications from TopHat pending in July needs checked - done
  • follow up on the rooms identified as at risk for insufficient capacity - done
  • follow up on NHS staff using Top Hat. - done - no further action here. Paul Clark informed.
  • decommission clickers system - done. SOftware removed from managed desktop.

Issues

  • none
  • no amber or red risks

Next Steps

  • closure  

Milestones

09-Sep-2015Project Closure
Project Status
RAG Status
Time
BLUE
Cost
BLUE
Scope
BLUE
Overall
BLUE
Change Status
Activity
Approved budget
30.0 days
Activity this month
0.5 days
Activity this year
0.5 days
Activity to date
21.0 days
Estimate to complete current year
1.0 day
Estimate to complete future years
0.0 days

Project Info

Project
Next Generation Personal Response System Implementation
Code
TEL023
Programme
ISG - Technology Enhanced Learning (TEL)
Project Manager
Maurice Franceschi
Project Sponsor
Mark Wetton
Current Stage
Close
Status
Closed
Start Date
09-Feb-2015
Planning Date
n/a
Delivery Date
n/a
Close Date
11-Sep-2015
Programme Priority
1
Overall Priority
Normal
Category
Compliance