Organisation

Work/Task Breakdown

Planning
  • Project Brief
  • Create project plan
  • Estimates
  • Stakeholders Identified
  • Risk Identified
Business Analysis
  • Collate, Review and Confirm Moodle Data Feed requirements
Design
  • Application Data Architecture Document
  • System Design
  • Update TAD and Ops Doc - EUGEX and MOODLE
Build
  • Build Activity
  • Deploy to Dev
  • Support  - CRON Job, read access to Moodle DB, Create separate MySQL database
  • Implementation plan
  • Unit / Integration tests
  • Peer Testing
  • Peer Testing Rework
Integration
  • System Design Document
  • Create Service in IDM, if required
  • Deploy to Test
  • Integration testing
  • Deployment checklist
Acceptance
  • User Acceptance Testing
  • UAT Support/ Rework
  • CReate Service in IDM, if required
  • Deployment checklist
  • System Documentation
  • Handover to Production
  • Acceptance Review
Deploy
  • Deploy to live
  • Deployment Review
Closure
  • Complete Closure Report

 

Resources Skills and Cost

  • IS Applications Developer
  • IS Applications Application Management
  • IS Applications Development Technology
  • IS Applications Technology Management
  • IS Applications Project Manager
  • IS Applications Programme Manager

 

Resource effort required but not included in the project estimate:

  • LTW Service Manager
  • LTW User Acceptance Testers
  • USD Helpdesk Support

 

Resource Effort Estimate is as follows: 50 days - this will be reviewed following delivery of Design and Application Data Architecture Document

  • IS Applications Developer / Resource Manager - 19.5 days
  • IS Applications Application Management - 4.5 days
  • IS Applications Development Technology - 7 days
  • IS Applications Technology Management - 2 days
  • IS Applications Project Services - 18 days

Project Info

Project
Moodle Course Enrolment Management
Code
TEL025
Programme
ISG - Technology Enhanced Learning (TEL)
Management Office
ISG PMO
Project Manager
Karen Stirling
Project Sponsor
Anne-Marie Scott
Current Stage
Close
Status
Closed
Start Date
20-Jul-2015
Planning Date
n/a
Delivery Date
n/a
Close Date
02-Sep-2016
Overall Priority
Normal
Category
Discretionary