July 2016

Report Date
July 2016

Achievements in Last Period

  • Build and integration milestones signed off
  • UAT milestone achieved
  • Deploy to LIVE achieved

 

Issues

  • Outstanding JIRAs need to be actioned becore we can get Deployment sign off and closure

 

Next Steps

  • Complete outstanding JIRAs
  • Re-deploy to LIVE
  • Achieve deployment sign off
  • Achieve Closure

 

Milestones

19-Aug-2016Deployment sign-off
24-Aug-2016Project closure
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
47.0 days
Activity this month
10.0 days
Activity this year
46.0 days
Activity to date
46.0 days
Estimate to complete current year
1.5 days
Estimate to complete future years
4.8 days

Project Info

Project
BlackBoard Collaborate MyEd Channel Refresh
Code
TEL032
Programme
ISG - Technology Enhanced Learning (TEL)
Management Office
ISG PMO
Project Manager
Chris Konczak
Project Sponsor
Anne-Marie Scott
Current Stage
Close
Status
Closed
Start Date
01-Feb-2016
Planning Date
n/a
Delivery Date
n/a
Close Date
08-Sep-2016
Programme Priority
5
Overall Priority
Normal
Category
Compliance