August 2016

Report Date
August 2016

Achievements in Last Period

  • Outstanding JIRAs completed and signed off.
  • Deployment to LIVE complete
  • Deployment sign off achieved
  • All have contributed to and are happy with the closure report. Closure sign off is waiting on the final TAD review, and is to be submitted to WIS for final approval on 09/09/16

 

Issues

  • Closure date moved from 24/08/16 to 09/09/16 due to JIRAs raised after deployment that required work, TAD updates required for closure, and buisness lead on annual leave on original closure due date. This has moved the project into AMBER. These have been resolved and the closure approval
  • Due to more JIRAs being raised and more devolopment time required, the project required an extra 6 days, hence cost is AMBER 

 

Next Steps

  • Achieve Closure

 

Milestones

09-Sep-2016Project closure
Project Status
RAG Status
Time
AMBER
Cost
AMBER
Scope
GREEN
Overall
AMBER
Change Status
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
BlackBoard Collaborate MyEd Channel Refresh
Code
TEL032
Programme
ISG - Technology Enhanced Learning (TEL)
Management Office
ISG PMO
Project Manager
Chris Konczak
Project Sponsor
Anne-Marie Scott
Current Stage
Close
Status
Closed
Start Date
01-Feb-2016
Planning Date
n/a
Delivery Date
n/a
Close Date
08-Sep-2016
Programme Priority
5
Overall Priority
Normal
Category
Compliance