September 2016

Report Date
September 2016

Achievements in Last Period

  • Closure

 

Issues

  • None
Project Status
RAG Status
Time
BLUE
Cost
BLUE
Scope
BLUE
Overall
BLUE
Change Status
Activity
Approved budget
53.0 days
Activity this month
0.5 days
Activity this year
7.0 days
Activity to date
55.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
BlackBoard Collaborate MyEd Channel Refresh
Code
TEL032
Programme
ISG - Technology Enhanced Learning (TEL)
Management Office
ISG PMO
Project Manager
Chris Konczak
Project Sponsor
Anne-Marie Scott
Current Stage
Close
Status
Closed
Start Date
01-Feb-2016
Planning Date
n/a
Delivery Date
n/a
Close Date
08-Sep-2016
Programme Priority
5
Overall Priority
Normal
Category
Compliance