Current project status

Report Date RAG Budget Effort Completed Effort to complete
April 2017 GREEN 132.0 days 124.4 days 1.1
Content
Status
Closed
Current Stage
Close
Start Date
Monday, 18 April 2016
Close Date
Friday, 19 May 2017
Project information
Project Code
TEL034
Programme
ISG - Technology Enhanced Learning (TEL)
Session
16/17
15/16
Organisational Unit
Learning Teaching and Web
Project Management Office (if relevant)
ISG PMO
Project Category
Discretionary
Programme Priority
3
Overall Priority
Normal