Report for April 2017

Report Date
April 2017

Achievements in Last Period

  • Further information gathered re Collaborate and Adobe connect
  • Final decision made to renew Collaborate License (Delivery milestone complete)
  • Discussion with Web team re additional user guidance
  • Project closure survey issued and closure report drafted

Issues

  • None

Next Steps

  • Project closure report to be approved
  • Actions after project closure - 
    • Short report for Russell Institutions
    • Virtual Classroom (Collaborate Ultra) vs Online Meeting (Skype for Business) guidance to be added to web pages
    • Collaborate License to be renewed from July 2017
    • Annual (brief) review of requirements and market to be managed by DLAM

Milestones

 

04-May-2017 Project Closure
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
21.0 days
Activity this month
1.5 days
Activity this year
13.5 days
Activity to date
13.5 days
Estimate to complete current year
1.5 days
Estimate to complete future years
0.0 days

Project Info

Project
Virtual Classroom - Options Appraisal and Procurement
Code
TEL042
Programme
ISG - Technology Enhanced Learning (TEL)
Management Office
ISG PMO
Project Manager
Karen McPhail
Project Sponsor
Josephine Kinsley
Current Stage
Close
Status
Closed
Start Date
14-Nov-2016
Planning Date
n/a
Delivery Date
n/a
Close Date
05-May-2017
Overall Priority
Normal
Category
Compliance

Documentation