Sep 2019

Report Date
September 2019

Achievements

  • The three bespoke VLEs are now in archive (read-only) mode and will be fully decommissioned in September 2020
  • learning.essq.ed.ac.uk was archived on 12th August 2019
  • learning.surgery.ed.ac.uk was archived on 1st October 2019
  • learning.ophthalmology.ed.ac.uk was archived on 1st October 2019
  • The Project Board has reviewed and approved the Project Closure report and most of the risks have now been closed.
  • The two open risks relate to the read-only archived sites, and it has been agreed that should there be a failure the sites may no longer be available.

 

 

Project Status
RAG Status
Time
BLUE
Cost
BLUE
Scope
BLUE
Overall
BLUE
RAG Commentary
All ESO programmes are now being delivered using BlackBoard Learn and the bespoke VLEs have been archived. The closure report has been agreed by the Project Board and risks have been closed apart from two ongoing risks - mitigation in place.
Change Status
Has formal escalation taken place?
Yes
Escalated to
Discussed at Project Board 13 Aug, 26 Aug, 04 July, 22nd May, 01 April. Agreed not to change the milestone dates, so they will continue to be flagged as red.
Change Commentary
Project Board discussed the overdue work at the meeting on 13 Aug. The Academic eFacilitator offered reassurance all changes would be made to week 1 content by the start of teaching. An additional meeting by Skype was organised for 26th August as a verbal checkpoint. Again the Academic eFacilitator was confident all changes would be made. Project Board discussed the overdue work at the meeting on 04 July The team has agreed that Semester 1 updates and induction/programme content should be prioritised as these must be completed before September. Semester 2 updates for all programmes except GCHM/TCHM are being delayed until later in 2019, and the project will close without these having been achieved. This does match the current work pattern of the Academic eFacilitators who update materials just before teaching starts.
Activity
Approved budget
68.0 days
Activity this month
7.0 days
Activity this year
94.0 days
Activity to date
94.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Edinburgh Surgery Online Learn go-live
Code
TEL056
Programme
ISG - Technology Enhanced Learning (TEL)
Management Office
ISG PMO
Project Manager
Karen Beggs
Project Sponsor
Anne-Marie Scott
Current Stage
Close
Status
Closed
Project Classification
Grow
Start Date
03-Sep-2018
Planning Date
31-Oct-2018
Delivery Date
16-Aug-2019
Close Date
27-Sep-2019
Overall Priority
Normal
Category
Discretionary