Overview
Background
The University’s strategy is to be a world leader in digital education, and to offer an outstanding student experience to as diverse a group of students as possible. We have specific targets around recruitment of non-EU international students and students from under-represented groups, as well as for student satisfaction with learning resources and academic support.
The University commissioned Headscape review in 2016 indicated clearly the inconsistencies across all our digital systems cause frustration and dissatisfaction for students. Senate Learning & Teaching Committee, in 2017, approved ISG to begin a VLE improvement project to address these areas of student feedback. Additional consultations in 2018 with academic & teaching office staff indicate that targeted support/training is required in order to make it easy to design the relevant course information to Learn.
This project will provide students with courses on Learn that meet their needs and provide the staff who design courses with the relevant skills, knowledge & guidance to do so.
Our vision is that: "Courses in Learn are accessible, and relevant information is easy to find by students. Staff find Learn easy to use, and are well supported to make and deliver rich courses online.”
Principles
-
Remove unnecessary complexity
-
Bring together all the information they need to do a task
-
Use simple language, without jargon or acronyms
-
Use task-based navigation (the same model used by GOV.UK)
-
Show students what they need when they need it
-
Show "Just in time" contextual help, reminders or prompts
-
Integrate existing data sources to present information that is useful to each individual student
-
Allow students to use whatever device they want
-
Use accessible design from the ground up
Scope
In scope
-
All campus based courses on Learn
-
Design & implementation of a solution that provides students with courses on Learn that meets their needs
-
Design & implementation of training/support that will provide staff who upload course content with the relevant skills, knowledge & guidance to do so
-
Improved integration of existing tools/systems into course design
Out of scope
-
Online only courses
-
Moodle & other VLEs although, as much as possible, solutions will be designed so that they are agnostic to platform
-
Redesign of the Blackboard Learn user interface
-
Changes to existing 3rd party systems that are integrated
-
Changes to existing integrations for 3rd party functionality/systems
-
Development of new tools/systems that could be integrated with Learn with the exclusion of Eesysoft
Objectives/Deliverables
Objective/Deliverable Ref |
Description |
Major Milestone |
MoSCoW |
In Scope |
O1 |
Project delivered with appropriate governance |
|
|
|
D1.01 |
Approved revised project brief |
No |
M |
Y |
D1.02 |
Re-baselined project plan |
No |
M |
Y |
D1.03 |
Planning complete |
Yes |
M |
Y |
O2 |
All stakeholders bought in |
|
|
|
D2.01 |
Identify stakeholders for communications |
No |
M |
Y |
D2.02 |
Complete stakeholder analysis |
No |
M |
Y |
D2.03 |
Agree communications plan |
No |
M |
Y |
D2.04 |
Ongoing delivery of communications according to plan |
No |
M |
Y |
O3 |
User consulted |
|
|
|
D3.01 |
Agree groups for consultation |
No |
M |
Y |
D3.02 |
Produce terms of reference for consultation |
No |
M |
Y |
D3.03 |
Form working groups for consultation |
No |
M |
Y |
D3.04 |
Ongoing consultation sessions |
No |
M |
Y |
O4 |
Identify solution(s) based on user needs & best practice |
|
|
|
D4.01 |
Identify users |
No |
M |
Y |
D4.02 |
Gather requirements from users |
No |
M |
Y |
D4.03 |
Identify & define possible solutions |
No |
M |
Y |
D4.04 |
Map current operating model from user(s) perspective |
No |
S |
Y |
D4.05 |
Project strategy brief outlining recommendations for solution(s) & 2 year plan |
Yes |
M |
Y |
D4.06 |
Agree plan |
Yes |
M |
Y |
O5 |
Inter-dependencies & integrations with Learn not negatively impacted by project |
|
|
|
D5.01 |
Identify projects, services, resources & initiatives that have a dependency or integration with Learn and/or that Learn has a dependency or integration with |
No |
M |
Y |
D5.02 |
Document dependencies & integrations |
No |
M |
Y |
D5.03 |
Ongoing review & appropriate communication with owners of relevant projects, services, resources & initiatives |
No |
M |
Y |
O6 |
Project benefits |
|
|
|
D6.01 |
High-level benefits documented |
No |
M |
Y |
D6.02 |
High-level benefits baselined and success criteria created |
Yes |
M |
Y |
D6.03 |
Set targets for improvements |
No |
S |
Y |
D6.04 |
Report on measurement against success criteria |
Yes |
S |
Y |
O7 |
Test agreed solution(s) to validate before roll out |
|
|
|
D7.01 |
Agree & document test scenarios |
No |
M |
Y |
D7.02 |
Agree testers & conclude usability/functionality testing |
No |
M |
Y |
D7.03 |
Testing complete & test results documented |
Yes |
M |
Y |
D7.04 |
Sign off outstanding bugs |
No |
M |
Y |
O8 |
Implement agreed solution(s) across all campus based courses in Learn |
|
|
|
D8.01 |
Agree implementation plan |
No |
M |
Y |
D8.02 |
Agree training/support requirements |
No |
M |
Y |
D8.03 |
Delivery/Implementation |
Yes |
M |
Y |
O9 |
Review project & document lessons learned |
|
|
|
D9.01 |
Agree participants to review with |
No |
S |
Y |
D9.02 |
Hold lessons learned workshops |
No |
S |
Y |
D9.03 |
Recommendations report outlining lessons learned |
No |
S |
Y |
O1O |
Checkpoints |
|
|
|
D10.01 |
Go/no go for testing |
Yes |
M |
Y |
D10.02 |
Go/no go for pilots |
Yes |
M |
Y |
D10.03 |
Go/no go for rollout |
Yes |
M |
Y |
O10 |
Project Closure |
|
|
|
D10.01 |
Agree arrangements for transition to service |
No | M | Y |
D10.02 |
Terms of reference for additional roll out |
Yes | M | Y |
D10.03 |
Closure Tasks |
Yes |
M |
Y |
Benefits
- Develop a deeper understanding of our user requirements and priorities with regards to use of Learn
This will be acquired via desk research and user consultation across all schools/colleges and using a wide representation of students.
Measured through collation of the following and presented as published report
- Previous UK and International research;
- User Experience analysis; and
- Consultation/feedback gathered via multiple methods, including surveys and focus groups.
- Improved student experience when using Learn - a consistent student experience where they find what they need, when they need it, and feel well supported in their studies.
Measured by case studies and surveys which will compare a baseline ( from existing survey data and case studies yet to be established) against post-implementation.
- Supporting the requirements of the Accessible and Inclusive Learning Policy (2016) through the introduction of templates & checklists.
Measured through Q&A activity which will identify the extent to which the templates & checklists have been adopted.
- Improved scaffolding and support for academic and professional services staff to develop courses on Learn in a way that supports a positive student experience with Learn, and creates a greater understanding of how Learn works to support their course context.
Measured by increased uptake of training/support materials, courses and positive feedback from school support staff.
Success Criteria
Methods of evaluation are currently being established and baselines gathered. Once this work is complete - milestone due 4th January - the below success criteria will be updated to include specifics where relevant.
- User satisfaction is improved in courses that adopt the improvements recommended – measured in a variety of ways (surveys, focus groups etc.) and measured against baseline (Quantitative & Qualitative)
- Delivery of key functionality required by the end users - measured against requirements gathered at outset (Quantitative)
- Adoption of templates - aim is to achieve 90% adoption of templates within 3 years with 1st year delivering 25%, 2nd year 75% and remaining 15% delivered through service in the final year(Quantitative)
- Improved connections within Learn User Group and other Learning Technology initiatives for sharing focussed interests in course development (Qualitative)
Project Milestones
The initial high-level milestones have been produced as an estimation of timelines based on implementation in 2019 however they will be updated & amended once planning is complete as this may change delivery deadlines.
May '19-September '19 will be focused on training, communications & supporting implementation in readiness for go live. The project activity required between September'19-January ’20, other than to complete measurement activity & create the report on findings, will be dictated by the implementation plan & level of support required. Phase 2 - from March '20 to Jan '21 will be dictated by the evaluation of Phase 1 and Scoping of Phase 2.
Stage | Milestone | Due Date | Previous Date | Complete |
---|---|---|---|---|
Plan | Project strategy brief outlining recommendations for solution(s) & 2 year plan (Major) | 31-Aug-2018 | No date available | Yes |
Plan | End of Planning | 05-Oct-2018 | 28-Sep-2018 | Yes |
Plan | Agree Detailed Plan | 02-Nov-2018 | No date available | No |
Plan | End of Detailed Planning | 02-Nov-2018 | No date available | No |
Design | Go/no go for testing | 04-Jan-2019 | No date available | No |
Analyse | High-level benefits baselined and success criteria created | 04-Jan-2019 | No date available | No |
Design | Testing complete & test results documented | 28-Feb-2019 | No date available | No |
Build | Go/no go for pilots | 01-Mar-2019 | No date available | No |
Accept | Go/no go for roll out | 03-May-2019 | No date available | No |
Deliver | Delivery/Implementation | 06-May-2019 | No date available | No |
Deliver | Report on measurement against success criteria | 10-Jan-2020 | No date available | No |
Deliver | Evaluation of Phase 1 complete | 28-Feb-2020 | No date available | No |
Deliver | Scoping of Phase 2 - Terms of reference produced | 27-Mar-2020 | No date available | No |
Deliver | Strategy Plan Document for Phase 2 | 29-May-2020 | No date available | No |
Deliver | Go/no go checkpoint for Semester 1 | 31-Jul-2020 | No date available | No |
Deliver | Go/no go checkpoint for Semester 2 | 27-Nov-2020 | No date available | No |
Close | Project Closure | 29-Jan-2021 | No date available | No |