Report for November 2020
- Report Date
- November 2020
Achievements in the last period
-
Continued data analysis from the Summer data collection.
-
Continued Phase Three work streams.
-
Continued to look at the School migration reports (x20).
-
Scheduled in Lesson Learned sessions for each College.
-
Begun Phase Three programme of engagement
-
Begun Phase Three programme of user experience
Issues
- None to report
Next Steps
-
Continue data analysis from the Summer data collection.
-
Continue Phase Three work streams.
-
Hold in Lesson Learned sessions for each College and prepare lessons learned reports.
-
Continue Phase Three programme of engagement
-
Continue Phase Three programme of user experience
Milestones
- Approved budget
- 500.0 days
- Activity this month
- 7.6 days
- Activity this year
- 11.9 days
- Activity to date
- 494.2 days
- Estimate to complete current year
- 10.6 days
- Estimate to complete future years
- 0.0 days