November Report

Report Date
November 2021

Achievements in the last period

  • Completed the phase three work streams.
  • Continued with the Learn Foundations Closure Activities - including hosting College lessons learned and completing closure report.
  • Begun the 'Evaluation' Work stream.
  • 'Upgrade to Learn Ultra' initiation activities continued.

Issues

No current issues identified.

Next Steps

  • Take closure paperwork to the final project board on the 15th December.

Milestones

Phase One: Evaluation Framework Sign Off

31-Jan-2022

Phase Two: Report on measurement against success (D9.03)

31-Jan-2022

Phase Two: Evaluation Baseline Completed (D9.01)

30-Jan-2022

Project Closure

31-Jan-2022

Phase Two: Evidence on Phase One completed - Report Produced (D9.04)

31-Jan-2022

Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Time
No Change
Cost
No Change
Scope
No Change
Overall
No Change
Has formal escalation taken place?
No
Activity
Approved budget
513.0 days
Activity this month
0.0 days
Activity this year
3.3 days
Activity to date
512.1 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Learn Foundations
Code
TEL057
Programme
ISG - Technology Enhanced Learning (TEL)
Management Office
ISG PMO
Project Manager
Lee-Ann Simpson
Project Sponsor
Melissa Highton
Current Stage
Analyse
Status
Closed
Project Classification
Transform
Start Date
27-Aug-2018
Planning Date
02-Nov-2018
Delivery Date
01-Jan-2022
Close Date
18-Jan-2022
Programme Priority
2
Overall Priority
Highest
Category
Discretionary