Organisation

Resources, Skills and Costs

LTW are providing resources for Senior User and Business Lead roles.

IS Applications are providing Project management, Software Development, Development Technology, Production Management and Service Management resources from the agreed funding.

Project Governance

Governance will be provided by the Project Team and the TEL058 Project Board will be advised about the progress of this project.  PMO will provide project Quality Assurance.

Project Stakeholders

Name                                      Role                                                     Business Area

Anne-Marie Scott                 Project Sponsor                                     DLAM

Karen Howie                          Senior User                                              DLAM             

Steph Hay                               Business Lead                                         DLAM

Dave Berry                              Senior Supplier                                      IS Apps

Ana Heyn                                 Applications Management Lead     IS Apps

Mark Lang                               Development Technology Lead      IS Apps

Heather Larnach                  Technology Management Lead       IS Apps

Geir Granum                          Software Development Lead            IS Apps            

Colin Watt                               Programme Manager                           IS Apps                        

Sonali Nakhate                     Project Manager                                     IS Apps                        

 

Project Estimations

The current high-level estimate for the project is 66.5 days of IS Apps time. 31.5 days is estimated for LTW time.

Link to three-point estimates.

 

Project Info

Project
Learn Upgrade
Code
TEL060
Programme
ISG - Technology Enhanced Learning (TEL)
Management Office
ISG PMO
Project Manager
Sonali Nakhate
Project Sponsor
Anne-Marie Scott
Current Stage
Close
Status
Closed
Project Classification
Run
Start Date
04-Mar-2019
Planning Date
15-Mar-2019
Delivery Date
17-Jul-2019
Close Date
09-Aug-2019
Programme Priority
2
Overall Priority
Normal
Category
Compliance

Documentation

Plan