Report for June 2019

Report Date
June 2019

Achievements in Last Period

  • Learn TEST upgraded to Learn Q4 2018 and Oracle database¬†patched,¬†testing of the upgraded environment ongoing.
  • Security scan carried out on learn TEST.
  • Relevant resources secured for July if Learn upgrade has to be carried out on Live self-hosted Learn, in case of issues with deployment to Cloud (TEL058 project)

Issues

  • No issues.

Next Steps

  • Testing on TEST Learn to be completed.
  • Decision to be made if this project will be made live depending on how Learn's migration to the Cloud goes.
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Time
No Change
Cost
No Change
Scope
No Change
Overall
No Change
Has formal escalation taken place?
No
Activity
Approved budget
50.0 days
Activity this month
8.0 days
Activity this year
0.0 days
Activity to date
22.3 days
Estimate to complete current year
10.0 days
Estimate to complete future years
3.3 days

Project Info

Project
Learn Upgrade
Code
TEL060
Programme
ISG - Technology Enhanced Learning (TEL)
Management Office
ISG PMO
Project Manager
Sonali Nakhate
Project Sponsor
Anne-Marie Scott
Current Stage
Close
Status
Closed
Project Classification
Run
Start Date
04-Mar-2019
Planning Date
15-Mar-2019
Delivery Date
17-Jul-2019
Close Date
09-Aug-2019
Programme Priority
2
Overall Priority
Normal
Category
Compliance

Documentation