Report for July 2019

Report Date
July 2019

Achievements in Last Period

  • Testing on TEST Learn┬ácompleted.
  • This project was a contingency project for TEL058 - Learn to the Cloud. Since Learn has been migrated successfully to the Cloud, deployment of this project to Live will not go ahead.

Issues

  • No issues.

Next Steps

  • Project to be closed.
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
BLUE
Change Status
Time
No Change
Cost
No Change
Scope
No Change
Overall
No Change
Has formal escalation taken place?
No
Activity
Approved budget
50.0 days
Activity this month
3.0 days
Activity this year
0.0 days
Activity to date
25.4 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Learn Upgrade
Code
TEL060
Programme
ISG - Technology Enhanced Learning (TEL)
Management Office
ISG PMO
Project Manager
Sonali Nakhate
Project Sponsor
Anne-Marie Scott
Current Stage
Close
Status
Closed
Project Classification
Run
Start Date
04-Mar-2019
Planning Date
15-Mar-2019
Delivery Date
17-Jul-2019
Close Date
09-Aug-2019
Programme Priority
2
Overall Priority
Normal
Category
Compliance

Documentation