Jun 2020

Report Date
June 2020

Work completed

  • Development work on feature enhancements completed, code reviewed and tested
  • Plugin for helpdesk roles tested
  • Documentation being updated ready for go-live
  • Change approved by Go-CAB
  • Service alert published

Issues

None

Next

  • Complete UAT on feature enhancements and helpdesk roles
  • Final preparation for go-live 9th July
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Time
No Change
Cost
No Change
Scope
No Change
Overall
No Change
Has formal escalation taken place?
No
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Academic Blogging upgrade 2020
Code
TEL067
Programme
ISG - Technology Enhanced Learning (TEL)
Management Office
ISG PMO
Project Manager
Karen Beggs
Project Sponsor
Karen Howie
Current Stage
Close
Status
Closed
Project Classification
Grow
Start Date
03-Apr-2020
Planning Date
23-Apr-2020
Delivery Date
02-Jul-2020
Close Date
24-Jul-2020
Overall Priority
Normal
Category
Discretionary

Documentation