March 2021

Report Date
March 2021

Last Month.

  • Zoom Test has now been setup which means the testing of the necessary changes to Single Sign On (SSO) can now proceed.

 

Issues.

  • No additional issues.

 

Next month.

  • Conduct the Test for changes to SSO.
Project Status
RAG Status
Time
AMBER
Cost
GREEN
Scope
GREEN
Overall
AMBER
RAG Commentary
The work between out ITI and Zoom to build the Zoom Test environment has proceeded slower than hoped. With that work complete we will be able to Test the SSO fix in April. The link of Zoom into Learn will then be straightforward as it has already been tested successfully.
Change Status
Time
No Change
Cost
No Change
Scope
No Change
Overall
No Change
Has formal escalation taken place?
No
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Zoom integration for teaching
Code
TEL072
Programme
ISG - Technology Enhanced Learning (TEL)
Management Office
ISG PMO
Project Manager
Colin Forrest
Project Sponsor
Karen Howie
Current Stage
Accept
Status
In Progress
Project Classification
Grow
Start Date
09-Dec-2020
Planning Date
31-Mar-2021
Delivery Date
02-Aug-2021
Close Date
16-Aug-2021
Overall Priority
Normal
Category
Discretionary

Documentation

Not available.