Report for March 2024

Report Date
March 2024

Achievements

  • 'Cannot connect..' error analysed by project team
  • Fix for error applied in LIVE
  • Fix successfully tested in LIVE
  • Deployment stage signed off
  • Closure report finalised and distributed for review

Issues

  • Final sign-off of closure delayed because of leave

Next Steps

  • Close project

 

Milestones

Close Project closure 28-Mar-2024

 

Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Time
Within Tolerance
Cost
No Change
Scope
No Change
Overall
Within Tolerance
Has formal escalation taken place?
No
Change Commentary
Small, unavoidable delay to project closure
Activity
Approved budget
100.0 days
Activity this month
0.9 days
Activity this year
8.2 days
Activity to date
107.5 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Blackboard Collaborate - MyEd Channel Improvements
Code
TEL079
Programme
ISG - Technology Enhanced Learning (TEL)
Management Office
ISG PMO
Project Manager
David Watters
Project Sponsor
Karen Howie
Current Stage
Close
Status
Closed
Start Date
01-Nov-2021
Planning Date
28-Jan-2022
Delivery Date
21-Mar-2024
Close Date
24-Apr-2024
Overall Priority
Normal