This project is required to coordinate an upgrade to the on-premise QMP application.
The procurement undertaken in the TEL068 E-Assessment Procurement and Implementation project was unable to deliver a replacement product, therefore QMP now requires an upgrade.
Current project status
Report Date | RAG | Budget | Effort Completed | Effort to complete |
---|---|---|---|---|
July 2022 | RED | 51.0 days | 15.0 |