This project is required to coordinate an upgrade to the on-premise QMP application.

The procurement undertaken in the TEL068 E-Assessment Procurement and Implementation project was unable to deliver a replacement product, therefore QMP now requires an upgrade.

Current project status

Report Date RAG Budget Effort Completed Effort to complete
October 2022 RED 51.0 days 37.8 days 13.4

Project Info

Project
QMP Upgrade
Code
TEL082
Programme
ISG - Technology Enhanced Learning (TEL)
Management Office
ISG PMO
Project Manager
Colin Watt
Project Sponsor
Karen Howie
Current Stage
Execute
Status
In Progress
Start Date
13-Jan-2022
Planning Date
31-Mar-2022
Delivery Date
20-Jan-2023
Close Date
17-Feb-2023
Overall Priority
Normal

Documentation

Project Dashboard

Project journal

No entries found.

Change dashboard

Nothing to report.