May 2020

Report Date
May 2020

Work completed

  • Purchase orders are ready and the team are working through the logistics of storage and installation costs (which would fall into next year).
  • The Learning Spaces team management have been in close contact with colleges to ensure we are adapting plans and purchasing kit that can be used during the current Covid situation.

Issues

  • Our future year funding has been removed, however this year's does stay in place.
  • Storage and installation, but as mentioned these points are being worked through.

Next Steps

  • Make the purchases of equipment.
Project Status
RAG Status
Time
AMBER
Cost
GREEN
Scope
AMBER
Overall
AMBER
Change Status
Time
Within Tolerance
Cost
Within Tolerance
Scope
Within Tolerance
Overall
Within Tolerance
Has formal escalation taken place?
No
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Specialist Teaching Spaces
Code
TSG004
Programme
Learning and Teaching Spaces (TSG)
Management Office
ISG PMO
Project Manager
Colin Forrest
Project Sponsor
Euan Murray
Current Stage
Execute
Status
Withdrawn
Project Classification
Grow
Start Date
03-Dec-2019
Planning Date
17-Jan-2020
Delivery Date
17-Jul-2020
Close Date
31-Jul-2020
Overall Priority
Normal
Category
Discretionary

Documentation

Not available.