By putting in place improved Disaster Recovery (DR) , this will reduce risk of extended downtime during a DR event, as Scientia infrastructure is extensive and distributed over multiple VM servers and requires many manual steps to recover the LIVE service to the DR site at AT. Potentially by putting in place improved DR , this will reduce the effort to keep the AT-side up-to-date after each upgrade. Effort will be saved if improved DR is put in place before the Scientia annual upgrade project. This adds some time urgency to complete TTU001 before TTU002 (Upgrade project).
Project is suspended until 31/01/14.
This project has now been withdrawn from the TTU programme.
Current project status
Report Date | RAG | Budget | Effort Completed | Effort to complete |
---|---|---|---|---|
October 2013 | BLUE | 50.0 days | 1.5 days | 48.5 |