Report for July 2014

Report Date
July 2014

Achievements in Last Period

  • Swtichover of the web applications is complete (4 August)
  • Switchover documentation complete and handed over to Technology Management

Issues

  • Learn outgoing interface has encountered a problem in test, awaiting resolution before deploying to live
  • Project reported as Red given carry over into 14/15 due to Learn feed failure

Next Steps

  • Deliver the Learn outgoing feed into Live
  • Project closure

Milestones

11-Aug-2014Outgoing Interface Switchovers Documented and Tested
15-Aug-2014Project Closed

 

Project Status
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Timetabling Annual Roll-Forward to 14/15
Code
TTU003
Programme
Timetabling (TTU)
Project Manager
David Watters
Project Sponsor
Scott Rosie
Current Stage
Close
Status
Closed
Start Date
13-Sep-2013
Planning Date
n/a
Delivery Date
n/a
Close Date
12-Sep-2014
Programme Priority
2
Overall Priority
Normal
Category
Compliance